Architect of the Capitol (AOC); the Baltimore District of the U.S. Army Corps of Engineers; John C. Grimberg Co., the contractor; and Einhorn, Yaffee and Prescott, the design firm. The new storage units will house 33 million items from the Library’s special-format collections, including 10 million manuscripts; 2.3 million prints, drawings, photographs and posters; 2.1 million music sheets; 542,000 maps and 1.8 million items from the collections of the American Folklife Center. The new sections were completed on schedule in June 2009—taking 28 months to build—and were within budget.